Current Photos - May 2010

 

Looking South towards downtown Everett:

 

 

 

 

 

 

 

 

 

 


Looking Southwest towards Mukilteo:

 

 

 

 

 

 

 

 

 

 


Looking West towards the Port of Everett:

 

 

 

 

 

 

 

 

 

 


Looking Northwest towards Tulalip:

 

 

 

 

 

 

 

 

 

 


View inside Sixth Floor, patient care:

 

 

 

 

 

 

 

 

 

 


Looking down the corridor that overlooks the rooftop garden:

 

 

 

 

 

 

 

 

 

 


A corridor in the Emergency Department with treatment rooms on either side:

 

 

 

 

 

 

 

 

 

 


Looking out over the rooftop garden:

 

 

 

 

 

 

 

 

 

 


Looking East down the First Floor concourse towards the parking garage:

 

 

 

 

 

 

 

 

 

 

 


Construction Timeline

Excavation began:
October 2008 

Tower cranes installed:
April 2009

Steel frame complete:
October 2009

Building shell complete:
August 2010

Construction complete:  2011

Currently working on:
Installation of passenger and service elevators. Wall studs in progress on all levels. Drywall board installment on levels B, G and 1-4. Ductwork, plumbing, sprinkler and electrical in progress on all levels.