Construction Update

 
Work Completed This Week - 6/21/09
• Roofing is complete at the balcony infill.
• Drywall taping is in process at PACU.
• Painting and ceiling grid is in process at Sterile Processing.
• Demo has started at the interior portion of the balcony infill.
• The fan and filter has been installed on the roof for the ED Isolation rooms.

Work Completed This Week - 6/14/09
• Metal panels at Stair S-01 penthouse are complete.
• Drywall has started at PACU.
• Taping has started at Sterile Supply.
• Spray fireproofing was completed at the balcony infill.
• MEP rough-in continued at Acute Care.

Work Completed This Week - 6/7/09
• Roofing at S-01 Penthouse is complete.
• CT Scan was completed and is back in operation.
• MEP continued at PACU and Sterile Processing.
• The balcony infill steel was installed.
• MEP continues in ED Treatment Rooms and ED Imaging.

Work Completed This Week - 5/31/09
• Penthouse construction continues at Stair S-01.
• Framing at Acute Care started.
• MEP continued at PACU and Sterile Processing.
• The north balcony infill was prepared for steel erection.
• X-ray support structure was completed in Rad 206.

Work Completed This Week - 5/24/09
• Penthouse construction started at Stair S-01.
• Piping over the CT Scan room in the E.D. was completed.
• Steel work at Stair S-01 continued.
• Demo at Acute Care continued.
• Flooring was installed at E.D. Waiting.

Work Completed This Week - 5/17/09
• Roof slab was cut open at Stair S-01.
• MEP continued at PACU.
• The duct enclosure was completed.
• New windows were installed at E.D. Waiting.
• Demolition started at Acute Care on the 2nd floor.

Work Completed This Week - 4/26/09
• ED Ambulance Entry was opened.
• Wall framing and MEP install continued at PACU.
• Demolition was completed at Endoscopy.
• A BRB was installed at Endoscopy.
• Demolition started at the Housekeeping Room near Sterile Supply.

Work Completed This Week - 4/12/09
• The Mammoth unit was removed and AHU/EF-2 was hooked up.
• Demolition at PACU South and Decontam/Sterile processing was completed.
• Rock was installed at the 2nd floor low roof.
• Demolition continued at Respiratory Therapy.
• One of the new BRB’s was installed.

Work Completed This Week - 3/29/09
• Art lanterns were installed at the lobby.
• Final changes and punch list work continues at the addition.
• Auto doors were installed at the ED remodels.
• ILSM work has started for the next phases of the remodel.
• Demolition has started at the old entrance.

Work Completed This Week - 3/1/09
• Punch list work continues throughout the addition.
• Casework installation continues throughout the 1st and 2nd floors.
• Carpet installation at the first floor is complete.
• Wood paneling at the Lobby has been completed.
• Cubicle curtains and window covering installation has started.

Work Completed This Week - 2/15/09
• The May Street stairs handrail was installed.
• The glass was placed at the entrance canopy.
• Installation of the tile at the main lobby was completed.
• Finishes and casework are being installed throughout the 1st and 2nd floors.
• Wall protection has been installed throughout the 1st floor.

Work Completed This Week - 2/08/09
• Landscaping continues around the addition.
• Glass canopy installation has started.
• Installation of the sunshade system has started.
• Ceiling tile has been installed throughout the first and second floors.
• Taping is nearly complete at the Chapel.

Work Completed This Week - 1/25/09
• Curtain wall system at the Gift Shop/Chapel is nearly complete.
• Flooring in Same Day is complete and flooring at the Family Birth Center has started.
• Site concrete around the addition is complete and the snow melt system is operational.
• Ceiling grid has been installed at the atrium/lobby.
• AHU/EF – 3 has been started.

Work Completed This Week - 1/18/09
• 2nd Floor curtain wall system and metal panels above are complete.
• Flooring in the Same Day Surgery corridors has started.
• The last of the snow melt system has been installed.
• Drywall taping has started throughout the atrium & lobby areas.
• Painting throughout the 2nd floor has started.

Work Completed This Week - 1/11/09
• A portion of the May Street stairs was poured.
• Metal panels have been completed.
• Windows are 90% complete.
• The southwest areas of the 1st and 2nd floors have drywall installed.
• Temporary occupancy has been obtained for the CUP.

Work Completed This Week - 12/7/08
• Concrete sidewalks were poured at the west alcove and the east stairs.
• Metal panel installation started on the south elevation.
• Curtain wall glass was installed at the 2nd floor.
• Flooring and casework installation continued in the lower level.
• Taping at the 2nd floor has started.

Work Completed This Week - 11/30/08
• Concrete sidewalk was poured at the north side of the addition.
• Snowmelt installation and forms were completed at the east stair.
• Curtain wall installation continues at the 2nd floor.
• Flooring and casework installation has started in the lower level.
• Drywall at the 2nd floor has started.

Work Completed This Week - 11/23/08
• The MRI magnet has been installed.
• Glass block was installed at the MRI window.
• Curtain wall installation has started at the 2nd floor.
• Ceiling grid install started at the north portion of the 1st floor.
• Sidewalk prep and snowmelt installation has started around the addition.

Work Completed This Week - 11/16/08
• Metal panels have been installed on the east & west elevations.
• Stone veneer work is complete on the addition and stairs.
• Casework has been installed in the MRI room.
• Church Lot parking has been completed.
• Drywall continues first floor & framing continues on the second floor.

Work Completed This Week - 11/9/08
• Metal panels have been installed on the north elevation.
• Stone veneer work on addition is complete. Work has started on  May St. stairs
• Water feature concrete is complete. Stone work will follow.
• Church lot walls and fine grading are ready for pavement.
• Drywall and taping continues on the 1st Floor.

Work Completed This Week - 11/2/08
• The east and south lots at the addition have been paved.
• Stone veneer work on the south elevation continues.
• Installation of the water feature continues.
• Retaining walls and excavation have been completed.
• Finishes have been installed in ED West remodel.

Work Completed This Week - 10/26/08
• Curbs and fine grading completed at the Addition Lots.
• Stone veneer work on the south elevation continues.
• Installation of the water feature continues.
• Excavation and retaining wall construction has started at the Church Lot.
• Steel entrance canopy has been erected.

Work Completed This Week - 10/19/08
• Curb work at the South Lot was completed.
• Stone veneer work on the south elevation continues.
• Installation of the water feature continues.
• The new approach and sidewalk was poured along 12th St.
• Drywall hanging and taping continues on the 1st Floor.

Work Completed This Week - 10/12/08
• Curb prep. at the Addition Parking Lot has started.
• Stone veneer work on the south elevation continues.
• Installation of the water feature has started.
• The HVAC units have been installed on the roof.
• Drywall installation has started on the 1st Floor.

Work Completed This Week - 10/5/08
• Grading at Addition parking lot continues.
• Stone veneer is being installed near the water feature.
• The crash wall at the east stair has been poured.
• Installation of the weather barrier continues.
• Sidewalks and curbs have been poured along 12th and May Street.

Work Completed This Week - 9/28/08
• Grading at Addition parking lot continues.
• Stone veneer has been installed on the CMU wall near the main entrance.
• The retaining wall at the May St. stairs has been poured.
• Installation of the weather barrier and furring at the metal panels has started.
• Installation of drywall in the lower level has started.

Work Completed This Week - 9/21/08
• Grading at the Church Lot continues.
• Framing of the main entrance was completed.
• Wall forming has started for the May St. stairs.
• RF shielding at the MRI Room was completed.
• Electrical equipment testing has started.

Work Completed This Week - 9/14/08
• Exterior stud framing continues.
• Clearing of the Church Lot has started.
• Footings were poured for the May St. stairs.
• EIFS patching was completed at the Lab BRB.
• Concrete was poured at the CUP stair pans.

Work Completed This Week - 9/7/08
• Exterior stud framing continues.
• The final storm line was completed.
• Interior framing and MEP work continues.
• BRB has been installed at near the Sleep Lab.
• Mechanical install at the CUP continues.

Work Completed This Week - 8/31/08
• Exterior stud framing continues.
• Exterior gyp. board is being installed.
• Interior framing and MEP work continues.
• BRB work has started near the Sleep Lab.
• Mechanical install at the CUP continues.

Work Completed This Week - 8/24/08
• Exterior stud framing continues.
• May Street retaining wall and backfill was completed.
• Interior framing and MEP work continues.
• BRB was installed at the Lab from the exterior.
• Mechanical install at the CUP continues.

Work Completed This Week - 8/17/08
• Exterior stud framing continues.
• May Street retaining wall work has started.
• Interior framing and MEP work continues.
• Louvers on the west side of the CUP have been installed.
• Mechanical install at the CUP continues.

Work Completed This Week - 8/10/08
• Pipe installation has started at the utility shaft.
• Roofing continues at the addition.
• Exterior stud framing has started at the north side.
• Stair installation at the CUP continues.
• Perimeter curbs have been poured.

Work Completed This Week - 7/27/08
• Cooling towers were installed at the CUP.
• Parapet framing was installed at the roof.
• Existing braces were replaced with BRB’s.
• Fireproofing of the steel continues.
• The 1st floor SOG was poured.

Work Completed This Week - 7/20/08
• 2nd floor slab south of J line was poured.
• The church was demolished.
• Mechanical installation continues at the CUP.
• Fireproofing of the steel continues.
• The 1st floor SOG was prepared for concrete.

Work Completed This Week - 7/6/08
• Roof slab north of H line was poured.
• Steel erection continues.
• Mechanical installation continues at the CUP.
• Fireproofing of the steel at the 1st Floor has started.
• Interior remodel work for ASI-51 continues.

Work Completed This Week - 6/29/08
• 2nd floor of the addition north of J line was poured.
• Steel erection continues.
• HVAC platforms were erected on the existing hospital.
• Fireproofing of the steel at the lower level was completed.
• Interior remodel work for ASI-51 has started.

Work Completed This Week - 6/22/08
• Concrete approach at 12th Street was completed.
• Steel erection continues.
• South entrance to Dethman was completed.
• Roof top AHU's were installed at the CUP.
• Stairs to the NW parking lot were completed.

Work Completed This Week - 6/15/08
• New washing machine installation was completed.
• Steel erection continues.
• 1st floor slab on metal deck was poured.
• ED Drive paving was completed.
• Stairs to the NW parking lot were demolished.

Work Completed This Week - 6/8/08
• MEP in the CUP continues.
• Steel erection continues.
• Loading Dock modifications continue.
• Curbs were installed along ED Drive.
• Remodel work continued in the Emergency Department.

Work Completed This Week - 5/25/08
• MEP in the CUP continues.
• Steel erection continues.
• Sidewalks along Prospect were poured.
• Protective enclosure was built around the exterior pipes near the ED.
• Remodel work continued in the Emergency Department.

Work Completed This Week - 5/18/08
• Paving at the CUP, Park & Prospect Lot, and Park & Prospect Steets.
• Steel erection continues.
• Roofing at the CUP continued.
• Equipment pads at the CUP were formed and poured.
• Final grading a curb work was completed east of the CUP.

Work Completed This Week - 5/11/08
• Landscaping continued at the Park & Prospect Lot.
• Structural steel and BRB braces arrived.
• Roofing at the CUP continued.
• Demolition of the existing skin.
• The rebuilding of Prospect St. started.

Work Completed This Week - 5/4/08
• Landscaping continued at the Park & Prospect Lot.
• MEP work continued in the tunnel and the CUP.
• The CUP SOG was poured.
• Slab prep at the lower addition was completed.
• The footings at the upper addition were formed.

Work Completed This Week - 4/13/08
• Interior column footings were poured at the lower addition.
• Curb work continued at the Park & Prospect parking lot.
• Under slab MEP work started at the lower addition.
• The second floor slab was poured at the CUP.
• Landscape sprinkler system is being installed/repaired throughout the site.

Work Completed This Week - 4/6/08
• Grade beam at the ’57 building was poured.
• Wall forms were stripped and placed for the next pour.
• Waterproofing and footing drains were installed at the /57 building and the addition.
• Spread footings at the lower level of the addition were formed.
• Steel erection at the CUP continued.

Work Completed This Week - 3/30/08
• A dry well was discovered and was pumped and removed.
• Wall forms were stripped and placed for the next pour.
• Waterproofing and footing drains were installed at the /57 building and the addition.
• New storefront doors were installed at the Imaging entrance.
• Steel erection at the CUP continued.

Work Completed This Week - 3/23/08
• Foundation walls were poured for the addition.
• Wall forms were stripped and placed for the next pour.
• Curbs and sidewalks were poured around ED Drive.
• Demolition and clean-up continued at the upper addition area.
• Concrete slab was poured at the Electrical Building.

Work Completed This Week - 3/16/08
• First foundation walls were poured for the addition.
• Wall forms were stripped and placed for the next pour.
• Grading and curb work continued throughout the site.
• Demolition and clean-up continued at the upper addition area.
• Concrete slab over the fuel tank was poured.